Triangle Associates, the construction management firm hired by the district, has developed a construction timeline for the bond projects. The timeline was approved by the Board of Education during the February BOE meeting.
PROJECT TIMELINE
Bids opportunities can be found on Triangle Associates website or on the Michigan Department of Management and Budget website.
You will find updates on all of the projects on this website.
STEEBY ELEMENTARY
- Construction is underway and is scheduled to be completed in September 09.
 Webelos from pack 3097 earning their Engineering Achievement
PINE STREET ELEMENTARY
- Ground Breaking Reception was held May 27, 2009 (see photos)
- Construction will begin in June 2009 and last through October 2009
- Projects went out for bid in February 2009
- Bids were approved during the March 2009 BOE meeting
- Drawings were approved by the Board of Education in November of 2008
- A Playground Design Team is currently involving students to help pick equipment
- Pine Playground Drawing
- Overview of Pine Street Projects
- For questions regarding the Pine Street project, please contact Principal, Jennifer Moushegian at 269-792-1127
HIGH SCHOOL

- High School Ground Breaking Ceremony was held on August 13 at 7p.
- View the construction progress on the WEBCAM
- The design teams for those areas have been meeting and touring other facilities
- High School Auditorium, Kitchen and Serving will go out for bid in June/July 2009
- Bleachers for the main gym will be replaced in Summer 2009
- Construction will begin for Auditorium, Kitchen and Serving in August 2009 and end November 2010.
- High School Stadium Renovation and Building Renovations will begin construction in May 2010.
- A list of high school projects are linked here
- Questions concerning high school projects can be directed to Principal, Tom Cutler at 269-792-2254.
BAKER ELEMENTARY
- Design teams are being formed and will begin meeting in Spring 2009
- Construction will begin May 2010
- A list of Baker projects are linked here
- Questions regarding projects at Baker Elementary can be directed to Principal, Celeste Diehm at 269-792-9208.
DORR ELEMENTARY
- Design teams are being formed and will begin meeting in Spring 2009
- Construction will begin in May 2010
- A list of Dorr projects are linked here
- Questions regarding projects at Dorr Elementary can be directed to Principal, Greg Rutten at 616-681-9637.
DISTRICT PROJECTS
- A new phone system was installed district wide in fall of 2008
- Four new buses will be purchased in the spring of 2009
- A Technology design team has been formed to plan the specific technology needs for each project as well as the district as a whole
- A playground design team will work on all elementary playground needs.
- For questions regarding general bond projects, please contact Superintendent, Eivor Swan or Assistant Superintendent of Finance & Operations, Jim English at 269-792-2181.
|
|